After nine months since August 2008, the process of reconstruction of houses destroyed during the Georgian aggression is ongoing. The School #5 building, which was badly damaged during the shelling of Tskhinval, is being reconstructed thanks to the humanitarian assistance provided by Arkhangelsk oblast.
”Electric nets and water pipes are being replaced and the school heating system is being installed. There are no delays with supply of construction materials for the school rehabilitation”, said Construction engineer Alexei Trishin.
“If the weather conditions allow, the reconstruction site will be ready by end of May. On 1 September, the schoolchildren will be able to come to a new school without any war traces,” he added. The reconstruction works at this site started on 16 September 2008. Due to delayed implementation of works, the agreement with North Ossetian sub-contractors had been terminated on 25 February 2009. Recently, the reconstruction of this site restarted and now “Olymp-Company” construction firm is dealing with it.